The
government has once again set out
to design an ambitious Annual Development
Programme (ADP) for the next fiscal,
which will lead to either increased
borrowing from the banking sector
or mopping up of public savings
through high interest bearing instruments.
Conversely, if the government perceivesthat
whatever may be the original size
of the ADP, in the end its utilisation
will be lower and so would be the
demand for resource generation,
this will also spell a 'programming
illusion'. Coined by Dr Debapriya
Bhattacharya, executive director,
Centre for Policy Dialogue (CPD),
"programming illusion" means a situation
in which neither the planning commission,
nor the line ministries would be
committed in project implementation
being aware of the implicit resource
constraint syndrome.
On balance, the country will continue
to remain hostage to high government
borrowing and ill-conceived projects.
Initially, signs were encouraging
as the Finance and Planning Minister
M Saifur Rahman slashed this year's
(FY02) ADP down to Tk 16,000 crore.
Many thought that it was a step
towards fiscal consolidation. Then
again, as the next fiscal's ADP
figures revealed things are taking
a different twist. As indications
go, the next ADP has been set at
Tk 19,000 crore. And this is not
final as the ADP is likely to incorporate
more projects, including one aiming
at increasing goat production in
the country and so it may be stretched
to Tk 19,500 crore. Even a Tk 19,000
crore ADP would mean an 18.8 per
cent growth over this year's revised
outlay, the highest jump since 1991.
The closest to such a growth was
in FY94 when the ADP spiked 18.2
per cent.
During the last five years of the
Awami League regime, the ADP remained
on a double-digit growth barring
FY98 when it increased by only 4.3
per cent. During the post-flood
period, in FY01, the government
however went in for an expansionary
spree yielding 17.9 per cent growth
in development spending. Now, looking
back at the revenue collection figures,
one will come across the fact that
never in the last one decade or
so revenue earnings had registered
a matching growth. Exception is
FY92 when resource mobilisation
witnessed a big jump of 21.7 per
cent thanks to the introduction
of VAT. But since then the result
is mostly double-digit growths on
the lower range barring some years
when it even dipped to single digits.
Revenue collection was especially
poor since FY96 when it clocked
a 9.2 per cent growth. In FY97 it
was 10.5 per cent, in FY98 it was
9.5 per cent, in FY99 it was even
as low as 4.9 per cent. During the
recent years, revenue growth rates
were 8.4 per cent and 13.2 per cent
in FY00 and FY01 respectively. "Revenue
receipt has not been able to keep
pace with public expenditure growth,"
said Dr Debapriya.
"Notwithstanding, public expenditure-GDP
ratio is one of the lowest in Bangladesh
compared to other developing countries
and the binding constraint is low
growth in revenue flow. This has
been accentuated by a low foreign
assistance flow in tandem with stagnation
in non-tax revenue collection. And
all these have landed the country
in a structural problem in the area
of public finance." Revenue budget
has however always remained quite
expansionary.
From FY96 to FY02, current expenditure
expanded on a double-digit growth
barring in FY97 and FY02. In FY96
it grew by 14.7 per cent, in FY97
by 6.1 per cent, in FY98 by 15.7
per cent and in FY99 by 15.6 per
cent. During the last two fiscals
(FY00 and FY01) revenue expenditures
increased by 10 per cent and 12
per cent respectively. And who knows
where it will end up in FY03 with
25,000 staff from different projects
being absorbed in the revenue budget.
"The absorption of staff from projects
into revenue budget is a paradoxical
stance since there is a hold on
recruitment of competent manpower
through the competitive BCS examinations.
In the long run, this will have
a bearing on the quality of governance,"
warned Dr Debapriya. "There is a
demand for infusing creativity in
the design of public expenditure
portfolio", continues Dr Debapriya.
"Opportunities could be created
for the private sector and the NGOs
to chip resources for infrastructure
development and poverty alleviation
projects. Revenue expenditure should
be put under a de facto moratorium
so that it does not increase in
real terms." "The tendency to increase
development expenditure without
a proper and credible project screening
process due to political reasons
also overrides whatever rudiments
of system are there.
The moot issue continues to be enhancing
quality, determining priorities
and ensuring effectiveness of public
expenditure." And so, when one sees
that the next year's ADP is also
going to include projects to support
the much-vaunted goat-breeding programme,
many an eyebrow are raised. In India
in the 1960s, a similar goat breeding
project was launched amidst a lot
of fan fare. And the result was
a sheer wastage of money as people
cheated on the government and took
credit just by showing the same
goats again and again. But the government
may always think that the size of
the ADP does not matter as long
as project implementation remains
as low as this year's. According
to third quarter implementation
figures of the IMED, the July-March
implementation rate of the ADP was
only 42 per cent, down from last
year's 54 per cent for the same
period. Of the total Tk 9410 crore
spending of the ADP during the period,
Tk 5671 crore was local currency
component and Tk 3739 crore was
in project aid. Now, if the government
thinks the same will happen with
next year's ADP, it might not have
to worry much about the revenue
implications. But then, low quality
projects and their protracted implementation
are equally damaging. "If the budget
is framed under demand side pressure,
it will have the tendency to result
in an over-ambitious revenue target
which will undercut the credibility
of the fiscal programming.
Alternately, a higher level of borrowing
from the banking system or savings
mop-up will become inevitable,"
the CPD executive director pointed
out. There are apprehensions that
continuation of the post-flood fiscal
trend underwritten by moderately
expansionary monetary policy will
snowball into increased public debt.
And, it will consequently result
in an increase in already high domestic
debt service liability, which is
now equivalent to about 16 per cent
of total revenue expenditure. "FY2003
should be a year of fiscal consolidation.
If we cannot revert the trend immediately,
we should at least hold it back.
Reducing the Tk 19,000 crore ADP
to Tk 16,000 crore was a nudge towards
that end. But if the ADP at stake
again goes as high as Tk 19,000
crore-plus then it will be a signal
missed," noted Dr Debapriya Bhattacharya.
The other logic for bigger public
expenditure could have been the
relatively low off-take of private
investment to generate domestic
demand. But experience of last couple
of years shows that the impact of
public expenditure in crowding-in
private investment has been limited
due to the absence of structural
and institutional reforms. Even
the low wage good prices could not
do the trick. "I trust that the
policymakers are aware of the situation.
They are possibly being compelled
to accommodate competing investment
demands coming from various interested
quarters. Taking cue from past experience
they are possibly assuming that
Tk 19,000 crore will not be spent
and so, there will be no need to
generate additional resources. They
are creating a programming illusion.
Programming and implementing agencies
won't be serious as even the Tk
16,000 crore revised ADP of FY02
may not be fully implemented." But
this will again be a wrong way of
managing public finance.
The cause of fiscal discipline will
be harmed. Possibly, the finance
ministry is being overridden by
certain political expediencies,
which undercut the integrity of
policymaking process in the country.
"Regrettably, over the period we
could not put in place a sound system
for initiating public expenditure
projects, to scrutinise their rationale
and develop their components which
will be insulated from interference
in allocative decision-making process.
"It was a general expectation that
the incumbent government will initiate
a transparent process which will
take a close and critical look at
public expenditure portfolio including
both on-hand and pipeline projects.
"Desirably it will be done by an
agency that is outside the system
having no vested interest in the
projects. Precisely for this reason
we advocated for a Public Expenditure
Review Commission. However, such
a commission will not be a substitute
for a sound internal control system,"
Dr Debapriya concluded.